Is combination of nodal pricing and average participation tariff the best solution to coordinate the location of power plants with lumpy transmission investments? - CentraleSupélec Accéder directement au contenu
Communication Dans Un Congrès Année : 2008

Is combination of nodal pricing and average participation tariff the best solution to coordinate the location of power plants with lumpy transmission investments?

Vincent Rious
  • Fonction : Auteur
Philippe Dessante

Résumé

This paper evaluates the opportunity and efficiency to introduce a two-part tariff to coordinate the location of power plants with lumpy transmission investments. Nodal pricing sends the short run component of such a two-part tariff and we study the case where the average participation tariff sends the long run one. We argue that this solution is helpful because the average participation tariff tackles lumpiness of transmission capacity while being as cost-reflective as possible. Our proposition is evaluated based on a double optimization model where a TSO minimizes the transmission cost while a generator minimizes its own cost that may take into account network constraints and include the average participation tariff. Numerical simulations are performed on a two-node network evolving during twenty years with increasing demand. The joint implementation of nodal pricing and the average participation tariff stays the best combination to coordinate as efficiently as possible the generation and transmission investments, although the optimal set of generation and transmission investments may not be reached because of transmission lumpiness. The simulations show also that implementing locational network tariffs is prioritary over implementing nodal pricing to coordinate more efficiently the location of generation with lumpy transmission investment. In the considered examples, the average participation tariff allows a more efficient location of generation even when the congestion management scheme being redispatch sends no short run locational signal.
Fichier principal
Vignette du fichier
Eval_interact_signx_loc_prod_Toulouse.pdf (455.23 Ko) Télécharger le fichier
Origine : Fichiers produits par l'(les) auteur(s)
Loading...

Dates et versions

hal-00323878 , version 1 (23-09-2008)

Identifiants

  • HAL Id : hal-00323878 , version 1

Citer

Vincent Rious, Yannick Perez, Philippe Dessante. Is combination of nodal pricing and average participation tariff the best solution to coordinate the location of power plants with lumpy transmission investments?. The Economics of Energy Market, Jun 2008, Toulouse, France. 23 p. ⟨hal-00323878⟩
137 Consultations
203 Téléchargements

Partager

Gmail Facebook X LinkedIn More